MINIMIZE

CONSTRUCTION UPDATES

Admiral Baysuites Construction Update for September 2013
Sep 22, 2013

Following its topping off ceremony on 07 June 2013, the overall construction works of Admiral Baysuites is now at 87% while the overall accomplishment status is at 65%.
In summary: waterproofing works is at 48%; the installation of balcony railings is at 15%; plumbing and sanitary works is at 83%; electrical works is at 60%; FDAS works is at 36%; auxiliary works is at 38%; mechanical works is at 51%; fire protection works is at 58%; the installation of glass, doors and windows in the East Wing is at 74% while it is at 36% in the West Wing; interior painting is at 29%; and the exterior painting is at 27%.
Admiral Baysuites is scheduled to be completed in 2014.        