Clairemont Hills Construction Update for September 2013
Sep 22, 2013

Clairemont Hills had its topping off ceremony on 30 August 2013. The event marked a construction milestone as it signifies that the structural works on the development’s 23 townhouse units and 16-storey residential tower has been completed.
As of 04 October 2013, the overall construction progress is at 50%.
At the main entrance gate and bicycle lane, on-going activities include the completion of greenwall and irrigation system, landscaping works, waterproofing works, tileworks, painting of the main entrance gate, and the application of washout finish for the plant boxes.
In the townhouses, the punchlist for unit 27 is currently being done, as well as general works in unit 26. On-going are the masonry, waterproofing, water tightness, and MEPF works in blocks 1 to 5. Meanwhile, structural works for block 4 is being completed.
At the tower, on-going activities include masonry works up to the 12th floor, tileworks, MEPF works, and preliminary works for swimming pool, elevator and the mock-up units.
Clairemont Hills is a gated residential enclave composed of a mid-rise residential tower and 23 townhouses. It is expected to be completed in 2014.