Admiral Baysuites Construction Update for August 2013
Aug 31, 2013

Following its topping off ceremony on 07 June 2013, the overall construction works of Admiral Baysuites is now at 84% while the overall accomplishment status is at 63%.
Areas that were completed in the month of August include the 8th floor and the 8th floor mezzanine.
 
For the MEPF works, the highlights include installation of feeder lines, meter centers, panel boxes, and kitchen exhaust and general wiring works.
 
For architectural works, the installation of wheel stop, non-skid tiles, and column guard is done. Concreting of curbs has also been completed. In the amenity area, the stairs leading up to the 8th floor mezzanine is finished, as well as general masonry works.
 
Painting works are still on-going, as well as the installation of ceiling frames, window frames, wooden jambs, and stair railings. Swimming pool preparation is still ongoing as well as the waterproofing of the kiddie pool and lap pool.
 
Admiral Baysuites is scheduled to be completed in August 2014.          