Admiral Baysuites Construction Update For June 2013
Jun 30, 2013

Admiral Baysuites had its topping off ceremony on 07 June 2013, Friday; announcing that the structural works on the heritage-rich edifice has been completed. MEPF works on the development are still on-going. Included in the works are the installation of feeder lines, panel boxes, CWL branches, downspouts, soil stack, aerator stack, interior sleeve refrigerant and kitchen exhaust, and water meters, among others. Current architectural works include the installation of non-skid tiles; waterproofing of the lap pools and children's pools; installation of ceiling frames, window frames, wooden jamps and doors; water proofing of toilet and baths; and various painting works. Admiral Baysuites is scheduled to be completed in August 2014.