MINIMIZE

CONSTRUCTION UPDATES

Admiral Baysuites construction update for June 2014
Jun 30, 2014

Structural works are DONE while mechanical, electrical, plumbing, fire protection, and architectural works are ongoing.

There is ongoing finishing works in the entire building, particularly in the lobby and the 8th floor amenity area. Punch listing and quality checks are also taking place.

In addition, we have recently removed the tower crane and three cabs of Alimak.

Construction is on-schedule for the Admiral Baysuites. It is expected to be completed in December 2014.

Admiral Baysuites is scheduled to be completed in 2014.  Allow us to keep you posted on Admiral Baysuites by liking www.facebook.com/admiralbaysuites and visiting www.admiralbaysuites.com.ph

 

 