Significantly, works in the final stages of accomplishment include the general construction works, waterproofing works, installation of balcony railings, plumbing and sanitary works, mechanical works, installation of glass doors and windows in the East Wing, and installation of cabinets and bedroom closets in the West Wing.
 
Also well underway are the installation of shower enclosures, supply and installation of stoneworks, electrical works, supply and installation of busduct system, FDAS works, auxiliary works, installation of glass doors and windows in the West Wing, elevator works, interior painting, and exterior painting.
 
Admiral Baysuites is scheduled to be completed in 2014.        