Admiral Baysuites Construction Update for October 2013
Oct 12, 2013

Construction of the Admiral Baysuites is making good time. The general construction works of Admiral Baysuites is now at 89% while the overall accomplishment status is at 67%.
 
In summary: waterproofing works is at 52%; the installation of balcony railings is at 27%; plumbing and sanitary works is at 86%; electrical works is at 65%; FDAS works is at 39%; auxiliary works is at 39%; mechanical works is at 56%; fire protection works is at 66%; the installation of glass, doors and windows in the East Wing is at 83% while it is at 43% in the West Wing; interior painting is at 32%; and the exterior painting is at 34%.
 
Admiral Baysuites is scheduled to be completed in 2014.      