MINIMIZE

CONSTRUCTION UPDATES

Anchor Skysuites Construction Update for August 2013
Aug 31, 2013

The overall accomplishment of Anchor Skysuites is at 88.48%. The accomplishment of the general contractor, on the other hand, is at 95%.
 
Highlights of the general contractor in the last month include casting of various RC walls, slabs, stairs, curbs and islands, and parapet walls; completion of fireproofing and insulation at TVR/LVSG Room; testing of transfer pump at the ground floor; generator set testing; and unitized panel testing.
 
Anchor Skysuites had its topping off ceremony on 1 December 2012, Saturday.
 
The target completion date of the project is in 2013.  