Anchor Skysuites Construction Update For June 2013
Jun 30, 2013

Overall accomplishment of Anchor Skysuites is at 84%. General contractor EEI Corporation already completed concrete pouring for the project. Balcony railings have been installed up to the 55th floor.

Likewise, floor tiles have been installed in the residential units up to the 52nd floor. Here are some of the progress highlights that are currently under way: waterproofing works and flood testing at the 56th floor, fit out works at the elevator lobby up to the 31st floor, and flood testing at the 31st floor floating lounge. Anchor Skysuites had its topping off ceremony on 1 December 2012, Saturday; announcing that the structural works on the sophisticated landmark has been completed. The target completion date of the project is in October 2013.