Anchor Skysuites Construction Update for March 2014
Mar 02, 2014

 

 

We have already begun the inspection of units from the 9th to 27th floor in preparation for the turnover. 23rd to 27th floors are for close out of punch list of all trades. 28th to 32nd floors are undergoing final paint. On the 33rd and 36th floors, painting works have already started. The 35th and 37th floors are due for augmentation of painting works. On the 38th to 55th floors, rectification works are being completed before the painting contractor commences works for final painting. On the 56th floor, softscape and stone works are on-going.

 

The Penthouse swimming pool is ready for use.

 

Exterior painting works is scheduled to be completed next month. 