Anchor Skysuites Construction Update for October 2013
Oct 31, 2013

As of October 2013, the overall accomplishment of Anchor Skysuites is at 92%. The accomplishment of the general contractor, on the other hand, is at 96%.
 
In the amenity areas, the 8th floor is 39% done, the 8th floor mezzanine is 48% done, the 31st floor is 58% done, and the 56th floor is 25% done. Majority of the works include wall cladding, ceiling works, installation of aluminum and glass, and landscaping. Overall accomplishment for the amenities is at 43%.
 
Anchor Skysuites is located along Ongpin St. Binondo, Manila. 