Clairemont Hills Construction Update for June 2013
Jun 30, 2013

Construction of Clairemont Hills remains to be on schedule. As of 24 May 2013, the overall construction progress is at 33%.

Bulk excavation works has been completed whereas the general construction works is at 55% and the plumbing and sanitary works is at 31%. Electrical works are 31% completed and the Fire Detection and Alarm System installations have progressed to 22%. Mechanical works is at 23% while the fire protection works of the development is at 27%. Aluminum and glass works is at 24% and landscaping works is at 17%.