Clairemont Hills Construction Update for March 2015
Apr 22, 2015

As of today, Clairemont Hills is close to exact completion at 99.45% .

The Clairemont Hills tower and all surrounding townhouses are all fully constructed. Blocks 2 and 3 of the Townhouse are ready for the unit-owners’ viewing while the tower’s 15th floor already has its first tenant. All the remaining floors are ready for the Turn-Over Department.

Quality issues on towers and townhouses paintwork were immediately addressed and corrected during the month of March. Lower and upper amenity floors, including elevator maintenance were turned-over to the property management group. Security and Technicians have been deployed.

Clairemont Hills is expected to be completed on May, 30, 2015.

To learn more about the property, visit the official website of Clairemont Hills.

 