Oxford Parksuites Construction Update January 2016
Jan 18, 2016

The Oxford Parksuites is now 69.63% completed. Construction is fully accomplished up to the 36th Floor level with on-going works at the 28th residential level (37th floor level).

For the past quarter, concreting works for 28 residential floor levels were completed as well as the CHB laying up to 16th residential floor and completed plastering works until 12th residential floor.  More works had been accomplished ahead of schedule such as wooden jamb installation of 9 floors, steel door installed up to the 20th floor level and painting of first coat at 2nd residential floor.

We can now see from the exterior are installed aluminum windows with glass and balcony railings.