Oxford Parksuites Construction Update September 2015
Oct 09, 2015

The Oxford Parksuites, moving a little ahead of schedule (33 days advanced) is now 55.17% completed. Construction are fully accomplished up to the 27th Floor with on-going form works at the 28th floor level.

For the past quarter, concreting works for 18 residential floor levels were completed as well as the CHB laying for the 9th to 17th floor (on-going at 18th floor). More works were done for the 9th – 11th floor including plastering works and installation of metal doors and wooden frame. Stair railings were also installed at the parking levels. Wooden jamb and tile installation shall follow in the coming weeks.

Target Project Completion remains at June 2017.

 