Oxford Parksuites Construction Update For June 2016
Jul 18, 2016

As of June 30, 2016 the Oxford Parksuites is 88.273% completed. From the façade, we can notice the completion of the precast works, exterior primer painting works is ongoing and the installation of windows at the 27th floor.

For the interior of the project, the residential tiling work is completed until the 19th floor while the tiling work of the residential Hallway is at the 16th floor and the Balcony at the 15th floor.

 

Interior primer painting is currently at the 20th floor and the interior 2nd coat painting is at the 10th floor. CHB (Concrete Hollow Block) laying is already at the 36th floor and will be completed in the next quarter while the Plastering works is completed until the 30th floor.

The construction is currently in full swing and we are glad to announce that the project is 22 days ahead of construction schedule.

 