Oxford Parksuites Construction Update For March 2016
Apr 11, 2016

The Oxford Parksuites is now 81.085% completed.

L-R: Mr. Geronimo L. Punzal , First Vice President of DM Consunji, Inc.; Engr. Reynaldo F. Villanueva Jr., AVP for Engineering of Anchor Land Holdings, Inc.; Ar. Alex Balean, Project Manager of ASYA Design; Mr. Luis C. Pastor, General Manager -Senior Vice President of DM Consunji, Inc.; Arch. Valerie Anne Patricia A. Consunji, Special Assistant to the President of DM Consunji, Inc.; Miss Digna Elizabeth L. Ventura-Sison, President of Anchor Land Holdings, Inc.; Mr. Steve Li, Vice Chairman & CEO of Anchor Land Holdings, Inc.; Mr. Jason Li, Board of Director of Anchor Land Holdings, Inc.; Engr. Rolando M. Policarpio, President of Prompt Managers & Construction Services Inc.; Engr. Felix R. Vigilia, Senior Project Manager of Anchor Land Holdings Inc.

The structural works have been fully accomplished during this period; we held a topping of ceremony last February 15, 2016.

The interior CHB (Concrete Hollow Block) laying is already at the 29th floor, while the plastering works have been accomplished until the 25th floor.

For the past quarter, the residential tiling works have been accomplished until the 12th floor and the tiling works of the balcony reached 9th floor. Moving forward to the Dry works, Installation of wooden doors is already at the 11th floor and the wooden jamb is at the 24th floor. Window frame and glaze installations are at the 20th floor.

As scheduled the exterior painting will begin this April, while the interior primer painting is already at the 20th floor and the Final coating is at the 9th floor.

We can now see from the facade that the structure of the Oxford Parksuites has been 100% accomplished. 