Oxford Parksuites Construction Update for October 2014
Oct 31, 2014

Significantly, the excavation of the whole area of Mat Footing (Foundation) has been completed. Concreting of another 40% mat footing has been done making a total of around 80% of Mat footing was concreted with a balance of 20%, expected to be completed in two weeks’ time.

Substantially, structural works are already completed; hence we are now starting to superstructures and expecting faster progress of concreting per floor level.

Oxford Parksuites is a learning-centered development that offers spacious homes along the Chinese School Belt in bustling Chinatown.

Site Aerial Photo showing Excavation and concreted Mat Footing, Cistern Tank and STP taken July 31, 2014

Site Aerial Photo showing Excavation and concreted Mat Footing, Cistern Tank, Ground Slab, Columns

Shear Wall and STP taken September 16, 2014

Photo showing concreted Fire Exit Stair and Elevator Shear Wall, taken September 30, 2014