As of December 30 2015, the substructure and foundation works for the Princeview Parksuites are completed. The project is moving as scheduled with an overall accomplishment of 23.99%.

Concreting works are nearing completion with the following status: ground floor at 100%, mezzanine at 100% and the 1st, 2nd, 3rd, 4th parking level is 100% completed.

The completion of parking floors up to 7th parking level is expected to be completed on February 2016, as scheduled concreting of residential floors will begin on March 2016. 

 