Princeview Parksuites Construction Update for September 2015
Oct 09, 2015

As of September 30, the substructure and foundation works for the Princeview Parksuites are completed. The project is moving as scheduled with an overall accomplishment of 19.94%.
 
Concreting works are nearing completion with the following status: ground floor at 92%, mezzanine at 84% and the first floor at 64%.
 
By the end of the year, concreting of parking floors (from mezzanine to 7th floor) is expected to be completed. Target Project Completion date remains at January 2018.