Princeview Parksuites Construction Update For June 2016
Jul 18, 2016

As of June 30, 2016, The Princeview Parksuites is 33.47% completed. The significant accomplishment during this period is the completion of structural works until the 14th floor and part of the 15th floor. 

The construction is moving ahead as scheduled.  The substructure/foundation works were completed which included the ground floor concreting at 100% and mezzanine to 7th   parking level. The structural work for the 8th floor amenity level is 100% completed.

People walking by the site can see the ongoing activities for 15th and 16th   floor typical residential floors.