Princeview Parksuites Construction Update for March 2015
Apr 22, 2015

To date, construction of Princeview Parksuites is in full swing.

The construction is on its infant stages and massive excavations are being done in preparation for the construction of the foundation. The first concrete pouring for the mat footing was fully accomplished last March 24, 2015.  Prior to that the completion of sheet piling were completed on the month of February 2015.

Zone 1 mat footing are fully concretized while rebar works are undertaken at zone 2 of construction. Expected completion of mat foundation on the remaining zones 3 and 4 , perimeter walls and final bulk excavation works are expected to be finished by July 28, 2015.

Target schedule for the completion of Princeview Parksuites is projected on January 2018.