The overall status of the completed construction works for Solemare Parksuites is at 88 %. Architectural works that are still on-going include the installation of toilet and bath floor tiles, flood testing, and the installation of ceiling frames, hallway tiles, doors, and kitchen cabinets.

Electrical works include electrical wiring for all residential floors. Plumbing and Sanitary works include the installation of floor drains, sanitary lines, cold water line looping and water meters. Fire protection works include the installation of sprinkler heads and the fire hose cabinets.