Solemare Parksuites Phase 2 Construction update for August 2013
Aug 31, 2013

The overall status of the completed construction works for Solemare Parksuites is at 89.51 %.
 
Structural works is at 100%.
 
For the on-going works: architectural works is at 81%. Electrical works is at 93%. FDAS and Auxiliary System is at 92%. Mechanical works is at 99%. Plumbing and sanitary works is at 96%. Fire Protection works is at 97%.
 
Solemare Parksuites Phase 2 is located in the Bay City, in between the SM Mall of Asia Complex and the up and coming PAGCOR Entertainment City. It will be completed in 2013.