Solemare Parksuites Phase 2 Construction update for March 2014
Mar 31, 2014

The structural works of Solemare Parksuites Phase 2 is complete.
Very few works remain before overall completion of the development. On-going architectural works include installation of countertops in remaining kitchens, punch listing at the 18th floor, and the installation of shower enclosures at the corner units on the 17th and 18th floors. For mechanical works and elevator works, we are conducting functional testing of ductless exhaust fan at the 17th and 18th floor. For electrical works, we're doing functional testing of power and lighting at the 15th and 16th floors. And lastly, for fire protection works, we're doing fire protection activation in the 9th, 10th, 11th, and 12th floors.
We have already started turning over some of the completed units.
Solemare Parksuites Phase 2 is located in the Bay City, in between the SM Mall of Asia Complex and the up and coming PAGCOR Entertainment City. 