As of 22 November 2013, the overall completion of Solemare Parksuites Phase 2 is at 96%.
 
For the on-going works: architectural works is at 95%; electrical works is at 98%; FDAS and Auxiliary System is at 96%; mechanical works is at 99%; plumbing and sanitary works is at 99%; and fire protection works is at 98%.
 
Solemare Parksuites Phase 2 is located in the Bay City, in between the SM Mall of Asia Complex and the up and coming PAGCOR Entertainment City. 