Solemare Parksuites Phase 2 Construction Update for September 2013
Sep 22, 2013

As of September 22, 2013, the overall completion of Solemare Parksuites Phase 2 is at 90%.
Structural works is at 100%.
For the on-going works: architectural works is at 84%; electrical works is at 95%; FDAS and Auxiliary System is at 94%; mechanical works is at 99%; plumbing and sanitary works is at 96%; and fire protection works is at 97%.
Solemare Parksuites Phase 2 is located in the Bay City, in between the SM Mall of Asia Complex and the up and coming PAGCOR Entertainment City. It will be completed in 2013.